Design and construction of balance of plant for two gas-fired co-generation units including hot water heat recovery boilers at EDF Toruń

EDF Toruń S.A.

Design, studies, purchasing fabrication, transport, erection, tests and commissioning of the balance of plant consisting of everything which is needed to achieve a complete new installation including in particular two hot water heat recovery boilers and district heating accumulator, but excluding two gas-fired gas turbines and several hot water boilers.
Detailed description of the object of the Works will be included in the Contract template, Technical Specification, constituting part of Terms of Reference, which will be released to the Economic Operators invited to participate in the tendering procedure.

Termin
Termin składania ofert wynosił 2013-10-21. Zamówienie zostało opublikowane na stronie 2013-09-25.

Dostawcy
Następujący dostawcy są wymienieni w decyzjach o przyznaniu zamówienia lub innych dokumentach dotyczących zamówień:
Kto?

Co?

Gdzie?

Historia zamówień
Data Dokument
2013-09-25 Ogłoszenie o zamówieniu
2013-10-16 Dodatkowe informacje
2014-07-30 Dodatkowe informacje
2014-10-20 Ogłoszenie o dobrowolnej przejrzystości ex ante