Design and construction of balance of plant for a new peak load heat generation plant at EDF Polska S.A. Krakow branch
Design, studies, purchasing fabrication, transport, erection, tests and commissioning of a new peak load heat generation plant (hot water) basically consisting of new building, connections to the district heating water system, electrical system, DCS system, new fuel oil storage tanks and associated pipework, and of everything which is needed to achieve a complete new installation excluding hot water boilers.
Detailed description of the object of the Works will be included in the Contract template, Technical Specification, constituting part of Terms of Reference, which will be released to the Economic Operators invited to participate in the tendering procedure.
Termin
Termin składania ofert wynosił 2014-02-18.
Zamówienie zostało opublikowane na stronie 2014-02-03.
Kto?
Co?
Gdzie?
Historia zamówień
Data |
Dokument |
2014-02-03
|
Ogłoszenie o zamówieniu
|
2014-02-14
|
Dodatkowe informacje
|
2014-02-26
|
Dodatkowe informacje
|
2014-12-11
|
Ogłoszenie o udzieleniu zamówienia
|